Before you can serve a good Notice to Owner, you need the Notice of Commencement. It is the recorded document that names the owner, the contractor, the lender and anyone else who must get your notice. Section 713.13 of the Florida Statutes says what it must contain, who signs it and how long it lasts. This guide covers those rules and how subcontractors and suppliers use the document on every job.

What a Notice of Commencement is

A Notice of Commencement is a short form the property owner records with the county clerk before work starts. Under section 713.13(3), recording it is not a lien or a cloud on the title. It gives public notice that construction liens may be recorded against the property, and it fixes where those liens stand in priority under section 713.07.

When it is required

Section 713.13(1)(a) says the owner or the owner's authorized agent must record the notice before actually starting an improvement, or before restarting after a default or abandonment. This applies whether or not there is a payment bond.

The main exception is in section 713.02(5): improvements where the direct contract price is $2,500 or less. Separately, the building-permit rules in section 713.135(1) do not apply to a direct contract to repair or replace an existing heating or air-conditioning system for less than $15,000.

After recording, the owner must post at the job site either a certified copy of the notice or a notarized statement that it was filed for recording, together with a copy. That is why the first place to look for it is the permit box or the front of the site.

What it must contain

Section 713.13(1)(a) lists the required information:

  • A description of the property: the legal description, plus the street address and tax folio number if available
  • A general description of the improvement
  • The owner's name and address and the owner's interest in the site, plus the fee simple titleholder if that is someone else
  • The contractor's name and address
  • The surety's name and address and the bond amount, if there is a payment bond under section 713.23
  • The name and address of any lender
  • The name and address of a person in Florida the owner designates to receive notices

Under section 713.13(1)(b), the owner may also name one more person to receive copies of lienors' notices. If a payment bond exists, section 713.13(1)(e) requires a copy of it to be attached when the notice is recorded.

The statute gives the form to use, in section 713.13(1)(d). Section 713.13(1)(g) says the owner must sign it and no one else may sign in the owner's place. For a company, the form's signature line is for an authorized officer, director, partner or manager. The form ends with a notary block.

How long it lasts

  • The 90-day rule. Under section 713.13(2), if the improvement is not actually started within 90 days after recording, the notice is void.
  • One year by default. The form says the notice expires one year after recording unless it states a different date. If the contract runs longer than a year, section 713.13(1)(c) requires the notice to say it is effective for one year plus the extra time.
  • Payments after expiration. Section 713.13(1)(c) says any payment the owner makes after the notice expires is considered an improper payment. Owners on long jobs record an amended notice before the first one runs out.

The building permit link

Section 713.135(1)(a) puts a warning on the permit card that begins: "WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY."

For a direct contract over $5,000, section 713.135(1)(e) requires the applicant to file a copy of the notice with the building department before the first inspection. A certified copy of the recorded notice works. So does a notarized statement that it was filed with a copy attached, or the clerk's instrument number or book and page. Without it, the department may not perform or approve later inspections. The permit office may not require the notice to be recorded before it issues the permit.

How subcontractors and suppliers use it

For a lienor without a direct contract with the owner, the Notice of Commencement is the address book for the Notice to Owner:

  1. Get a copy on day one: from the job-site posting, the permit file, or the county clerk's official records search by owner name or address.
  2. Copy every name and address exactly: owner, contractor, lender, the designee for notices and any copy designee.
  3. Note the recording date and the expiration date, and look for amended notices.
  4. Write down your first day of furnishing labor, services or materials. Your Notice to Owner is due within 45 days of that day under section 713.06(2)(a), and mailing by day 40 gives you the certified-mail protection in section 713.18(2).
  5. Serve to the addresses on the latest notice. Section 713.18(3) lets you use the building permit application or the last known address when no notice was recorded.

This guide is general information, not legal advice. For a dispute on a specific job, talk to a Florida construction attorney.

Sources: Florida Statutes section 713.13, section 713.135 and chapter 713 (2026 text).

FloridaNTO turns the names and addresses from the Notice of Commencement into a Notice to Owner in the statutory wording, with your deadline: see the plan.

Need the Notice of Commencement itself? It is the owner's form. The owner can prepare the statutory form on our sister site PermitReady FL (self-help, $19), then sign, notarize and record it.

The form itself: the Florida Notice to Owner form, part by part, with a filled sample.

Official sources cited in this guide

Checked against Florida Statutes · Published November 21, 2026 · 4 min read