Florida Contractor's Final Payment Affidavit (713.06)
Notice to Owner forms and lien deadlines for Florida subcontractors and suppliers. From $39, one time.
See plansOn most Florida jobs the last check does not move until the contractor hands the owner a sworn paper: the contractor's final payment affidavit. Section 713.06(3)(d) of the Florida Statutes says when the contractor must give it, what it must say and what the owner may do with it. For subcontractors and suppliers, it is also the moment a Notice to Owner pays off, because the affidavit has to list you if you served your notice on time and are still owed money. This guide explains the rules from both sides.
What the final payment affidavit is
It is a sworn statement from the contractor to the owner. It says either that every lienor under the contract who served a Notice to Owner has been paid in full, or which of them have not been paid and how much each is owed. The statute supplies the form. It ends with a notary block that reads "Sworn to and subscribed before me", so the contractor signs it under oath before a notary.
When the contractor must give it
- When final payment becomes due. Section 713.06(3)(d)1. opens with "When the final payment under a direct contract becomes due the contractor" and then lists the affidavit duty.
- At least 5 days before suing. The same subparagraph requires the affidavit "at least 5 days before instituting an action as a prerequisite to the institution of any action to enforce his or her lien".
- No affidavit, no lien action. While the contractor is in default for not giving the affidavit, the statute says "the contractor shall have no lien or right of action against the owner" for the work under that direct contract. A negligent mistake or omission in the affidavit that has not prejudiced the owner is not a default that defeats an otherwise valid lien.
- Also when the contract ends early. The 5-day rule applies even if final payment has not become due because the contract was terminated for a reason other than completion, and whether or not the contractor has any lienors working under it.
For a contractor waiting on a final check, the affidavit is not optional paperwork. The statute makes delivery at least 5 days before suit a condition of any action to enforce the contractor's lien, so the delivery date matters and is worth being able to prove.
What it must say
The affidavit covers "all lienors under his or her direct contract who have timely served a notice to owner on the owner and the contractor". For each of those lienors who has not been paid in full, it must show the lienor's name "and the amount due or to become due each".
- Only timely notices count. The list is limited to lienors who served a Notice to Owner on time, on both the owner and the contractor. A supplier who never served one is not on it.
- Future money counts too. The amount includes what is already due and what is still to become due under that lienor's work.
- It is sworn. The contractor signs before a notary, so the numbers should match the contractor's own payment records.
What the owner can do with it
- Rely on it, with one exception. Section 713.06(3)(d)4. says "The owner shall have the right to rely on the contractor's affidavit given under this paragraph in making the final payment, unless there are lienors giving notice who are not listed in the affidavit." If a lienor who served a Notice to Owner is missing from the list, the statute lets the owner pay those lienors and the listed lienors entitled to payment, and then be discharged except for any balance still due the contractor.
- Pay listed bills directly. If the affidavit lists unpaid lienors, the owner may, "after giving the contractor at least 10 days' written notice, pay such bills in full direct to the person or firm" owed, when the balance due on the contract is enough to cover them.
- Short balances. If the balance due is not enough to pay every listed lienor and every lienor who gave notice, section 713.06(3)(d)3. says the owner pays no money to anyone until the contractor furnishes the difference; if the contractor does not do so within 10 days, the owner determines the amount due each lienor and disburses under subsection (4). An owner in that position may want to talk to a Florida construction attorney.
- Hold the final payment until it arrives. Section 713.06(3)(d)5. says the owner "shall retain the final payment due under the direct contract", which "shall not be disbursed until the contractor's affidavit" has been furnished.
Why it matters to subcontractors and suppliers
- Serve your Notice to Owner on time. It is due within 45 days of your first day of furnishing labor, services or materials under section 713.06(2)(a). Under section 713.18, service by certified mail is effective on the mailing date if it is mailed within 40 days after your first furnishing and you keep the USPS mail log or tracking record. See the 45-day rule and how to serve a Notice to Owner.
- Serve the owner and the contractor. The affidavit language covers lienors who served "on the owner and the contractor". Keep the receipts and tracking for every copy you send.
- Keep your balance in writing. Send invoices and statements so the contractor's "amount due or to become due" for you matches your records.
- Check before the final payment. Near the end of the job, you can ask the owner or the contractor whether a final payment affidavit has been given and whether you appear on it with the right amount.
- Be careful with final waivers. Sign a final waiver and release of lien only for money you have actually received. Our lien waiver guide covers the section 713.20 forms.
The affidavit does not move your lien deadline
Your claim of lien deadline is set separately. Section 713.08(5) says a claim of lien may be recorded "not later than 90 days after the final furnishing" of your labor, services or materials. If the direct contract is terminated under section 713.07(4), the deadline can come sooner: 90 days after termination or 90 days after final furnishing, whichever occurs first. Nothing in section 713.06(3)(d) extends either date, so the deadline runs whether or not the contractor has given an affidavit. Our guide to Notice to Owner vs. claim of lien explains how the two steps fit together.
Checklist for contractors
- Collect every Notice to Owner served on you for the job.
- For each of those lienors, confirm paid in full, or write down the amount due or to become due.
- Complete the statutory form, sign it before a notary and deliver it to the owner when final payment becomes due.
- Keep proof of the delivery date; the statute requires delivery at least 5 days before any suit to enforce the lien.
This guide is general information, not legal advice. For a dispute on a specific job, talk to a Florida construction attorney.
Sources: Florida Statutes chapter 713 (2026 text): sections 713.06(2)(a) and 713.06(3)(d), 713.07(4), 713.08(5), 713.18 and 713.20 (read 22 Nov 2026).
FloridaNTO's generator puts the facts you type into the statutory Notice to Owner wording and calculates your 45-day deadline, so you can serve on time and be one of the lienors the affidavit must cover: see the plan.
The form itself: the Florida Notice to Owner form, part by part, with a filled sample.
- chapter 713 (flsenate.gov)