Notice to Owner vs. claim of lien in Florida
Notice to Owner forms and lien deadlines for Florida subcontractors and suppliers. From $39, one time.
See plansFlorida's construction lien law uses two documents that are easy to confuse. The Notice to Owner comes at the start of a job and preserves your right to a lien. The claim of lien comes at the end, only if you are not paid, and is the lien itself. Missing the first usually makes the second worthless, and the second has its own deadlines that keep running after the job is over. This guide puts the two side by side, with the dates that control each one.
Side by side
| Notice to Owner | Claim of lien | |
|---|---|---|
| Purpose | Tells the owner you are on the job and have lien rights | Places a lien on the property for the amount unpaid |
| Who uses it | Subcontractors, sub-subcontractors and suppliers without a direct contract with the owner | Any lienor who is unpaid and has preserved its rights, including contractors |
| Deadline | Before you start or within 45 days of first furnishing, and before the owner's final payment (s. 713.06(2)(a)) | Within 90 days after your final furnishing (s. 713.08(5)) |
| Where it goes | Served on the owner, with copies as the statute requires | Recorded with the clerk in the county where the property is, then served on the owner |
| What follows | Nothing, if you are paid | Serve the owner within 15 days of recording; sue to enforce within 1 year |
Notice to Owner: early and preventive
Under section 713.06(2)(a), a lienor without a direct contract with the owner (other than a laborer) must serve the owner before commencing, or not later than 45 days after commencing, to furnish labor, services or materials, and before the owner disburses final payment. Sub-subcontractors and suppliers to a subcontractor also serve the contractor. The notice gives your name and address, describes the property and says what you are furnishing. It is not a demand for money and it does not mean anyone is behind on payment. See the 45-day deadline explained for how to count the days.
Claim of lien: late, if unpaid
A claim of lien is recorded in the official records of the county where the property is located. Section 713.08(1) requires it to state, among other things:
- Your name and address for service
- The name of the person you contracted with
- The labor, services or materials furnished and the contract price or value
- The legal description of the property and the owner's name
- The dates of your first and last furnishing
- The amount still unpaid
- The date and method of service of your Notice to Owner (or of the copy on the contractor), if one was required
That last item is where the two documents meet: the claim of lien asks you to show that the Notice to Owner was served, and when.
The deadlines after the job ends
90 days to record
Section 713.08(5) says the claim of lien may be recorded during the work but not later than 90 days after your final furnishing of labor, services or materials. There is a separate rule for terminated contracts: if the original contractor defaults or the contract is terminated, a claim for work furnished before that date may not be recorded more than 90 days after the termination. Corrective or warranty work after the job is complete generally does not extend the 90 days; check the definition of final furnishing in section 713.01 before relying on a late date.
15 days to serve the owner
Under section 713.08(4)(c), the recorded claim of lien must be served on the owner. Failing to serve it within 15 days after recording can make the lien voidable.
1 year to sue, or 60 days if the owner contests
Under section 713.22(1), a lien lasts no longer than 1 year after the claim of lien is recorded unless an action to enforce it is started in court within that time. Section 713.22(2) lets the owner shorten that period by recording a notice of contest of lien: the lienor then has 60 days from service of that notice to sue, or the lien is extinguished automatically.
Contractors: the final payment affidavit
A contractor in direct contract with the owner does not serve a Notice to Owner, but section 713.06(3)(d) requires a final payment affidavit, delivered to the owner at least 5 days before the contractor sues to enforce its lien.
A worked timeline
A drywall subcontractor starts on a job on March 3, 2027 and finishes on August 20, 2027, and the last invoice goes unpaid.
- March 3, 2027: first furnishing. Notice to Owner mailed by certified mail on March 5, well inside 40 days.
- August 20, 2027: final furnishing. The 90-day clock for a claim of lien starts.
- November 18, 2027: last day to record a claim of lien.
- Within 15 days of recording: serve the recorded claim of lien on the owner.
- Within 1 year of recording: start a lawsuit to enforce it, or settle. If the owner records a notice of contest of lien, the window shrinks to 60 days from service of that notice.
Mistakes that cost lien rights
- Serving the Notice to Owner after day 45, or after the owner has already paid the contractor in full
- Counting the 90 days from the invoice date instead of the last day of work or delivery
- Recording the claim of lien but never serving it on the owner
- Letting the 1-year enforcement period run out while waiting for payment
- Claiming more than is actually owed. Only claim the unpaid amount; a willfully exaggerated lien can be treated as a fraudulent lien under section 713.31
Keep good records
Log your first and last day on each job, delivery tickets, invoices and every certified mail receipt. Those dates decide every deadline above. FloridaNTO prepares the Notice to Owner and a service record page for each job; it does not prepare claims of lien. If you need to record a claim of lien or enforce one, talk to a Florida construction attorney.
This guide is general information from the 2026 Florida Statutes, not legal advice.
Next: the 45-day Notice to Owner deadline and how to serve it. Check your dates with the free deadline calculator.
The form itself: the Florida Notice to Owner form, part by part, with a filled sample.
- section 713.06(2)(a) (leg.state.fl.us)
- Section 713.08(1) (leg.state.fl.us)
- section 713.22(1) (leg.state.fl.us)
Checked against Florida Statutes · Published November 20, 2026 · 5 min read